Unit Costs

This page contains the Equipment, Material, and Labor Unit Costs used by the model to calculate activity-specific Per Mile Costs. Unfortunately, at this time, the user is not able to edit these Unit Costs. However, the user has the ability to override the activity-specific Per Mile Costs that are calculated based on these unit costs.

Equipment

unit costs 01 equipment

Material

unit costs 02 materials

Labor
  • Laborer Grp 1: $180.00
  • Operator Grp 2: $200.00
  • Operator Grp 3: $200.00
  • Prod Foreman: $225.00